Parallel Machine Scheduling with Fuzzy Processing Times and Sequence Dependent Setup Times: An Application in a Textile Company

dc.contributor.author Gülce Çini
dc.contributor.author Ayhan Özgür Toy
dc.contributor.author Önder Bulut
dc.contributor.editor C. Kahraman , S. Cevik Onar , B. Oztaysi , I.U. Sari , A.C. Tolga , S. Cebi
dc.date.accessioned 2025-10-06T17:50:10Z
dc.date.issued 2022
dc.description.abstract The textile company we consider receives orders from customers for different types of products and with different quantities. The company has several production lines as a “machine” and an order for a product type as a “job” to comply with the scheduling terminology. We assume that not all machines are suitable for processing all jobs i.e. jobs can only be processed on their eligible machines. When there is more than one eligible machine those machines are identical in terms of their setups and processing times. We assume that all jobs and machines are ready to be processed at time zero. We also assume that the times required to set up the machine for the next job depend on the job completed and the job in order hence setup times are sequence-dependent. The processing time of a job is not deterministic due to various factors such as operator learning curve and fatigue and machine maintenance requirements. Likewise setup times also vary depending on human and technical factors. We choose to model these uncertainties by assuming fuzzy processing times and fuzzy setup times. Our objective is to assign and schedule jobs to minimize the makespan the completion time of the last job. Our solution approach relies on the comparison of solutions through a randomized search algorithm a Monte Carlo simulation with an improvement routine. We conduct a numerical study and present the solution quality of the proposed methodology. © 2022 Elsevier B.V. All rights reserved.
dc.identifier.doi 10.1007/978-3-031-09173-5_23
dc.identifier.isbn 9789819652372, 9783031931055, 9789819662968, 9783031999963, 9783031950162, 9783031947698, 9783032004406, 9783031910074, 9783031926105, 9789819639410
dc.identifier.issn 23673389, 23673370
dc.identifier.uri https://www.scopus.com/inward/record.uri?eid=2-s2.0-85135083694&doi=10.1007%2F978-3-031-09173-5_23&partnerID=40&md5=5289582d3345769b88cd5ff8a698612c
dc.identifier.uri https://gcris.yasar.edu.tr/handle/123456789/8805
dc.language.iso English
dc.publisher Springer Science and Business Media Deutschland GmbH
dc.relation.ispartof International Conference on Intelligent and Fuzzy Systems INFUS 2022
dc.source Lecture Notes in Networks and Systems
dc.subject Application In Textile Industry, Fuzzy Processing Times, Fuzzy Setup Times, Parallel Machine Scheduling, Scheduling
dc.title Parallel Machine Scheduling with Fuzzy Processing Times and Sequence Dependent Setup Times: An Application in a Textile Company
dc.type Conference Object
dspace.entity.type Publication
gdc.bip.impulseclass C5
gdc.bip.influenceclass C5
gdc.bip.popularityclass C5
gdc.coar.type text::conference output
gdc.collaboration.industrial false
gdc.identifier.openalex W4285301400
gdc.index.type Scopus
gdc.oaire.diamondjournal false
gdc.oaire.impulse 0.0
gdc.oaire.influence 2.3811355E-9
gdc.oaire.isgreen false
gdc.oaire.popularity 1.6828513E-9
gdc.oaire.publicfunded false
gdc.openalex.collaboration National
gdc.openalex.fwci 0.0
gdc.openalex.normalizedpercentile 0.23
gdc.opencitations.count 0
gdc.plumx.mendeley 4
gdc.plumx.scopuscites 0
gdc.virtual.author Toy, Ayhan Özgür
oaire.citation.endPage 183
oaire.citation.startPage 177
person.identifier.scopus-author-id Çini- Gülce (57212207923), Toy- Ayhan Özgür (14521673500), Bulut- Önder (35168573500)
publicationvolume.volumeNumber 504 LNNS
relation.isAuthorOfPublication 40d5f673-8a20-4e1f-b0a3-777528129295
relation.isAuthorOfPublication.latestForDiscovery 40d5f673-8a20-4e1f-b0a3-777528129295
relation.isOrgUnitOfPublication ac5ddece-c76d-476d-ab30-e4d3029dee37
relation.isOrgUnitOfPublication.latestForDiscovery ac5ddece-c76d-476d-ab30-e4d3029dee37

Files